Apartments and rental properties

SB 721 balcony inspections

California law requires owners of covered apartment buildings to hire a qualified inspector to check certain balconies, decks, exterior stairs and other raised outdoor structures. The inspector checks the supports and the parts that keep water out. The owner must act on unsafe conditions and keep the inspection records.

Does SB 721 apply to your building?

Check each building on its own. Look at the property records, the number of homes in the building and the way its outdoor structures are built.
  • Three or more homes in one building

    Count the residential dwelling units in the same building. A triplex can qualify. Shops and offices do not count as homes, but mixed-use buildings can qualify.
  • A qualifying exterior elevated element

    The building must have at least one qualifying raised outdoor structure with load-bearing parts. Check its height, use and support materials.

Which balconies, stairs and decks count?

SB 721 calls these structures Exterior Elevated Elements, or E3s. It lists balconies, decks, porches, stairways, walkways and entry structures, including their supports and railings. An element qualifies under the statewide rule when all four points apply:

  • It extends beyond the outside wall of the building.
  • Its walking surface is more than six feet above ground level.
  • It is built for people to use.
  • Wood or wood-based products provide all or a substantial part of its support or stability.

Check the frame below the surface. Tile or concrete can cover wood supports. A local program can cover additional materials or structures. Read the SB 721 definition or find local rules.

When is the inspection due?

  • Existing buildings

    The general first deadline was January 1, 2026. The statewide cycle repeats by January 1 every six years. If your building is covered and has no qualifying report, arrange the inspection promptly and check local filing requirements.
  • Newer buildings

    If the building permit application was submitted on or after January 1, 2019, the first inspection is due within six years after the certificate of occupancy. Use the building’s permit and occupancy records to check the date.

Who can inspect and what do they check?

The owner hires a California-licensed architect, civil engineer, or structural engineer, a contractor who meets SB 721’s license and experience requirements, or a professional with a certification that meets the local jurisdiction’s requirements. A contractor needs an A, B, or C-5 license. At least five years of experience constructing multistory wood-frame buildings while holding a qualifying license.

South San Francisco’s balcony inspection guide lists these certifications:

  • Certified Building Inspector, ICC B5 or equivalent.
  • Certified Building Official, ICC CB or equivalent.

For the SB 721 certification route, confirm that the local jurisdiction accepts the certification and recognizes the issuing association. The inspector must not be employed by that jurisdiction while performing the inspection.

Use the official directories to check a contractor license with CSLB, check an architect license with CAB, check a civil or structural engineer license with BPELSG, or verify an ICC certification. Inspector qualifications.

The inspector examines the parts that carry the load and the parts that protect them from water. The law allows direct visual examination or a comparable method. The inspector looks for signs such as rot, damaged connections, water entry and changes that weaken the structure.

The inspector must check at least 15% of each type of qualifying element. For example, 20 balconies and 10 exterior stairways require at least three balconies and two stairways. Ask how the inspector will reach hidden supports and when they would need to open a covered area. See how the 15% sample works.

What happens after the inspection?

The inspector must give the owner or the owner’s agent a signed or stamped report within 45 days after completing the inspection. It must include photos, any test results, and enough detail to compare the condition with later inspections. It describes current condition, expected service life and any need for further inspection. It also identifies immediate hazards and required safety measures.
  • Immediate danger

    Block occupant access and take required safety measures immediately. The inspector must send the urgent report to the owner and local enforcement within 15 days after completing the report. Use a contractor licensed for the wood, steel, concrete or waterproofing repair, obtain required permits and have the inspector check the emergency repairs and report them to local enforcement.
  • Repairs without immediate danger

    Apply for a permit within 120 days after receiving the report. Complete the repairs within 120 days after permit approval, unless local enforcement grants an extension. Hire a contractor whose license covers the repair materials and work and follow the inspector’s recommendations and local requirements.

    If the owner fails to comply with the repair requirements within 180 days, the inspector must notify the owner and local enforcement. If repairs are still incomplete 30 days after that notice, the law calls for a daily penalty of $100 to $500 until completion, unless local enforcement grants an extension. Ask the local agency about deadlines and any extension before time runs out.

Keep the report and repair records

Keep the inspection reports for at least two inspection cycles. Later reports must include prior reports and identify which elements were inspected. Keep permits, repair records and any final report with them. Give the inspection reports to the buyer when you sell the building. Your city or county may also require filing the initial report, the final report or both. See what belongs in the report.

Plan your inspection budget

Count the elements by type and share previous reports, plans and photos you can take safely. Explain how the inspector can reach each area and where tenants need advance notice. Ask each provider to price the same scope, including any openings, how they will be closed, the report and follow-up visits. See the inspection quote checklist.

Prepare before you request a quote

Start with location, role, and known elements

Keep this short. Enter a California city or ZIP, choose the role or question, then add only the element categories you know.

0Total entered
0Elements to inspect
0Uploaded media

Counts should cover the project. The inspection count is the minimum number of elements to plan around for this request.

SB 721 planning count uses at least 15% of each same-type element entered here.
?

SB 721 uses ceil(total same-type elements x 0.15). SB 326 uses Z = 1.96, e = 0.05, and p = 0.5 when unknown. Section 604 and other request types use the total entered here. This is quote-planning support, not a final inspection plan or legal advice.

Health and Safety Code 17973Civil Code 5551San Francisco Section 604

Add only the categories you know. Leave unknown element types out for now.

Quote statusProvider quote needed
Inspected-count assumption0 of 0
Full-inventory count0
Show count assumptions
TypeEnteredEstimated inspected
Balconies00
Decks00
Stairs00
Landings00
Walkways00
Rails00
Fire escapes00

The count assumption is not a price. Public sources do not support a reliable market price for every element type yet. A real quote still depends on provider pricing, access, building layout, local process, reporting scope, and whether the inspector expands the sample.

This is not a provider quote, regulated fee schedule, market average, legal advice, engineering advice, safety determination, or compliance certification.

Common SB 721 questions

Start myPROJECT